PROJECT

DCAM Amsterdam Park offers modular warehouse space to accommodate the needs of todays dynamic occupiers.

Project Scope

  • To be delivered in two 20,000 m2 phases, each consisting of two separate buildings
  • Either phase can be brought forward independently. Construction of building 1 started in January 2018
  • Total GLA up to 40,000 m2
  • Modular warehouse space, offering units of 16,600m2 plus office and mezzanine
  • Designed to achieve BREEAM rating ‘Excellent’.
    Take a look at the case study

Timetable

  • Construction works for Phase I started in January 2018
  • Completion of the Phase I facility is anticipated in quarter one of 2019
  • Phase II will start upon finalisation of Phase I (or earlier depending on client request)
  • Early access for tenant fit-out during the final construction phase can be offered

Project Progress Phase 1

April 2018
  • Base ground works completed
  • Foundation piling ongoing
May 2018
  • Foundation piling completed
  • Foundation works ongoing
June 2018
  • Foundation works completed
  • Construction of loading area substructure ongoing
July 2018
  • Floor piling ongoing
  • Started steel construction works

Warehouse Overview

  • Free storage height of 12.2 m
  • Column span of 23 m (optimised for both narrow and wide aisle racking configurations)
  • One loading dock per 850 m2 of warehouse space
  • Automated electric doors on ground floor level (4 m x 4.2 m)
  • Average floor load capacity of 5,000 kg/m2 with maximum point load of 80 kN
  • Flatness floor according to DIN 18202 Tabel 3, Zeile 4
  • Certified ESFR sprinkler installation according to NFPA
  • Fire separation between the two units or multiple units depending on configuration
  • Fire hose reels, fire alarm and evacuation system
  • LED lights equipped with dynamic dim function, delivering 200 Lux at 1.5 m
  • Charging station for lift trucks – 1 station per 1,000 m2 of warehouse